About Milestones

Until recently, I thought that the concept of a milestone is basically self-explaining, but it seems that I was wrong. On two different occasions, I was told that even trained project managers sometimes cannot tell the difference between an activity and a milestone.

In my opinion, milestones represent one of the most important concepts of project planning, monitoring, controlling and reporting. A milestone provides you (as the project leader) with the ability to define a specific point in time where your project reaches a defined status. Without milestones it is very hard to tell how "far" you actually are with executing a given project plan.

In many project planning tools, the difference between a milestone and an activity is simply that the milestone has zero length, i.e., it starts and finishes at the same point in time. However, semantically, there is a lot more to it why an activity and a milestone are two completely different things:

  • An activity defines a unit of work, i.e., what has to be done, by whom, with a defined start and finish date. For instance, "create a project plan" could be an activity. An activity can be between 0% and 100% complete, since progress can be measured within the activity
  • A milestone defines a specific status which should have been reached within the scope of the project, typically indicating that some work or phase has been completed, e.g., "project plan created" could be a milestone. A milestone cannot be 50% complete; it is either open (0%) or it is closed, i.e., completed (100%) - there is nothing in between
Milestones

Milestones are typically shown in schedules in the form of a diamond where an empty diamond indicates an open milestone, while a filled diamond denotes a closed/completed milestone.

This semantic difference should also be reflected in the naming of activities and milestones: I personally use the present tense to name activities while I use the past tense to name milestones. Typical examples for milestone names could be "design finished", "implementation completed", or "handbook reviewed".

The most common practical application of a milestone is as a delimiter of a phase within a project plan. A project phase is a top level activity or collection activity (often also referred to as a "work package"). Such milestones can then be used for monitoring and controlling the overall project progress using milestone tables, or more advanced tools such as a milestone trend analysis (we will cover this topic in a future post in more detail).

Finally, the most important milestone of a project is probably the completion of the given project. Therefore, it is good practice to include an explicit "project completed" milestone. This milestone can be used to formally conclude the project and might remind you to think again if your project is really complete, or whether you have forgotten about something... have you? ;-)

Comments on this article

Melanie Mersmann wrote on March 10, 2007 at 14:02 GMT

Good arguments, but you can also validly argue, that if a milestone is "design finished" that would be equivalent, to the activity "design application" is 100% completed. And even, if you have multiple activities like "design businesslogic" and "design userinterface" you can still model it apropriately via making both dependent for a task "merge design". There should be more about milestones and from my opinion, there is. Normally you make projects for a client (either an explicit one but also inside a company). And it is obvious, that the client has to execute some tasks here as well. But normally they would not let them be included in the project-plan. Thus as a rule of thumb it is quite smart to have a milestone for every obligation to cooperate of the client beeing due. Also because normally that would also block proceeding with the dependent tasks.

Gerald Mesaric wrote on March 10, 2007 at 14:26 GMT

Very good comment, thanks. I especially agree about let's call them "external" milestones, or "obligations" as you named them.

Christian Philipps wrote on March 11, 2007 at 16:30 CET

I could not agree more with Melanie on the use of milestones for prerequisites. Normally you would also use some additional document such as a prerequisites-log linked to these milestones. Business partners sometimes like to ignore the impact of them failing to fulfill their own obligations in time ... using milestones for visualising this impact in the project plan makes it easier to bring the message across. Another aspect of milestones worth writing about could be best practices for using milestones for project plan segmentation and visualisation. Milestones can help for example to summarize key dates in a section of their own right at the top of the project plan (if one likes this style).

wrote on April 3, 2007 at 17:12 GMT

Gerald Mesaric wrote on April 6, 2007 at 18:44 GMT

I am about to write a follow-up article about milestones; I will try to cover some of these aspects (we are still in "newbie" mode here, so I do not want to go into too advanced topics in detail yet).

Custom blog design wrote on January 4, 2010 at 13:02 CET

Great aspects!

vanzari auto wrote on February 23, 2010 at 06:24 CET

I think moust of people didn t know the different.
It is bad because if they new that they will understand how this things works.

make money online wrote on February 24, 2010 at 19:13 CET

thanks for all the great data i love it

travel guide wrote on March 5, 2010 at 00:55 CET

I do agree, much work is needed.

ugg outlet wrote on March 6, 2010 at 08:52 CET

Replica watches http://www.watchesxm.com
ugg outlet http://www.uggsoutletstores.net
cheap ugg http://www.uggs-outlet.org
nike shoes http://www.shoesucn.com

roulette du casino wrote on March 19, 2010 at 14:21 CET

The milestones have been chosen with the help of 56 experts in the field, listed in the 'advisors' section, who were each asked to select the most significant papers in their own area of expertise. These suggestions were compiled, and the top 23 discoveries were chosen as the milestones. These milestones are not intended to be comprehensive reviews - rather, they highlight a discovery (or series of discoveries) that represents a conceptual advance in the field. The milestones have been written by editors from the Nature Publishing Group, and reviewed by the panel of advisors.

earn money online wrote on April 9, 2010 at 14:20 CEST

nice blog really like it

Carlton Woods wrote on April 10, 2010 at 23:46 CEST

To me, a milestone is when you come to a definable/measurable point along a journey. Whether it is a big project or a hike up a mountain, you know when you get there and it can help you keep focused on the journey. I think everyone hits milestones whether they call it one or not. For instance, a birthday is a milestone. When someone turns 50, they are a big milestone in life whether they like it or not.

black hills gold rings wrote on April 16, 2010 at 15:41 CEST

This article is really very nicely written and clearly explained..

Leave a comment

Plase note: Due to massive comment spamming, I have taken comments offline for the time being.