My Projects

June 5, 2008 3 comments so far

More Controlling: Standard PMI/PMBOK Terms

Let's round up the resource and cost controlling topic by taking a quick look at what standard terms the well-known PMBOK Guide defines regarding "Cost Control: Tools and Techniques" ;-).

I have to admit that I normally do not use the standard terms as defined by the Project Management Institute (PMI) in their "Guide to the Project Management Body of Knowledge" (PMBOK Guide). The major reason for this is that typically only experienced project managers know their meaning and for most people, common terms are simply easier to understand.

However, if you are talking to a senior project manager who knows the PMI terms, you have the advantage that you can communicate in a more exact way and prevent potential misunderstandings. The abbreviated terms also come in handy if you need "small" labels, e.g., for table headers in more complex reports.

  • Planned value (PV) is what I called "baseline" in my previous post, i.e., the planned/budgeted/negotiated value
  • Actual cost (AC) is of course "actual"
  • Estimate at completion (EAC) is equal to my "projection"
  • Estimate to complete (ETC) is the estimated cost for the remaining work required in order to complete the work package or project, i.e., EAC = AC + ETC (in our case; the PMBOK also describes other, more complex forecasting methods)
  • Earned value (EV) is something slightly more complex (you might have heard about "earned value project controlling") and worth a separate post on another day... ;-)

Please note that deviations are called "variances" in the PMBOK Guide. The standard PMI terms for the deviation I described in my previous post might be variance at completion (VAC) against planned value (but defined vice versa as PV - EAC). However, I am not 100% sure here, since I could not find the proper definition in the PMBOK.

This brings me to a question for you: I have seen several definitions for deviations/variances some resulting in a positive value when you are above budget, some resulting in a negative value. Which one do you prefer and why?

Comments on this article

Anonymous wrote on August 3, 2009 at 12:07 CEST

Fantastic thank you. Find the files you are looking for at my-dvdrip.com the most comprehensive source for free-to-try files downloads on the Web

Tim wrote on August 14, 2009 at 06:40 CEST

Nice blog.
A couple of quick definitions of variances that might help.
VARIANCE AT COMPLETION
VAC =Budget - EAC
(ie Variance at Completion is a way of measuring how you are expecting to against your overall budget.)

EARNED VALUE
EVA = a calculation to determine the Budgetted cost of works complete. (ie, if you have completed 60% of a $100 project, your EVA is $60)

CURRENT VARIANCE
CV=AC-EVA
(Current Variance measures your actual expenditure against your budgetted expenditure) at this moment (rather than the overall performance as in VAC).

Generally, (at least in my world) CV & VAC are read in conjunction with each other. To continue my earlier example, if you have only expended $50 of your $100 activity, your CV would be -$10. If you EAC was $92, then VAC & CV are telling a consistent story (ie, you are running underbudget, and will continue to do so).

However, if your EAC was $115, then it should be raising some alarm bells for the Project Manager, as you are currently underbudget, but expecting to go over budget overall. In this case, the Project Manager might be wanting to ask whether the Physical % complete is correct, or whether actual costs are being understated (and why), or whether a "balloon" of costs is expected in the last bit of the project, or whether the Estimate to Complete is incorrect....and so on.

In combination VAC & CV can act as a flag to say "are the financial parts of the project (or individual activity) progressing as we expected?

ugg outlet wrote on March 6, 2010 at 08:40 CET

Replica watches http://www.watchesxm.com
ugg outlet http://www.uggsoutletstores.net
cheap ugg http://www.uggs-outlet.org
nike shoes http://www.shoesucn.com

Leave a comment

Plase note: Due to massive comment spamming, I have taken comments offline for the time being.